Works completed in Feb 2022.
We were requested by our client to remove the concrete canopy and columns to the front of Number 1 Knightsbridge by means of Controlled Demolition.
We used a 330 Robotic demolition machine (Brokk) to crunch down the concrete and finished of with a track saw cut to leave a smooth finish to the remaining slab.
Due to the location of the site between ‘The Wellesley’ and ‘The Lanesborough’ hotels works had to be carried out in selected noisy work periods which were 2 hours on 2 hours off.